Designing Formwork to Reduce Construction Costs
Good formwork is critical for fast-paced construction and keeping
costs under control. By following simple rules in the preliminary layout
and design of a project, the cost of concrete construction can be reduced,
sometimes dramatically.
Here are some cost-saving suggestions on formwork:
- Select
one framing scheme and stick with it for as long as pobbile - even throughout the project. Two framing
schemes can only be justified on a large project.
- Arrange member
sizes and spacing so that the capacity of minimum-sized members is
fully used.
- Use architecturally exposed concrete framing. The extra cost of more
careful formwork, details, steel and concrete placement may be less
than other
options such as stone.
- Orient framing in one directing for one-way systems,
such as beams and joists to save time on the job.
- Use "flying
forms" to form large areas of walls or floors where
the forms can be moved in large sections and reused many times—up
to 20 or more.
- Space columns uniformly for repetitive production line setting.
Make all columns the same size, vertically in one stack as well as
horizontally in one story. Vary the amount of reinforcement and concrete
strength to
achieve size-uniformity.
- Make all beams and joists the same depth. The savings
in formwork and shoring will exceed any cost increase in concrete and
steel.
- Use
standard form sizes for one-way and two-way joists because non-standard
sizes need to be specially fabricated.
- Allow reasonable tolerances and specify tight tolerances only where
they are needed since they require more field labor.
- Locate construction joints
where the contractor wants them with as little restriction by the engineer
as possible. This enables the contractor to
select the most efficient sequence of pours for the construction method
used.